We are planning a mail upgrade coming up and I have a quick question on the process.

We have a two server set up.

One MTA
One Mail store server (LDAP is here)

All documentation that I see says upgrade the servers in this order:

LDAP
MTA
Mailbox store

So my question is, do I only upgrade the LDAP on the first server (mailbox store) and then upgrade the MTA server. After completing the MTA server, I then go back and finish the rest of the install on the Mailbox store?

So my process would be this:

1. LDAP on mailstore server only
2. MTA
3. Mailbox store - finish remaining upgrades.

Thanks for any help,

Rich


User avatar
L. Mark Stone
Elite member
Elite member
Posts: 2140
Joined: Wed Oct 09, 2013 11:35 am
Location: Portland, Maine, US
ZCS/ZD Version: 8.8.15 Network Edition
Contact:

Re: Upgrade from 8.6 to 8.8.15 Multi Server

Postby L. Mark Stone » Tue Apr 07, 2020 5:44 pm

Hi Rich,

Your mailbox/LDAP server should be upgraded in its entirety first, then upgrade the MTA server right afterwards.

Hope that helps,
Mark
___________________________________
L. Mark Stone
Mission Critical Email - Zimbra VAR/BSP/Training Partner https://www.missioncriticalemail.com/
Zeta Alliance http://www.zetalliance.org/

Return to “Installation and Upgrade”

Who is online

Users browsing this forum: No registered users and 7 guests